Now One we can manager manage PowerBI apps in WIP

Pre-requisite

...

  1. Login as VMMANAGER and go to server

  2. Click on Add server and select Power BI

  3. Enter the details as below

  4. Name: Name of the server
    Directory (tenant) ID - id of the tenant
    Application (client) ID - client id
    Secret Key - secrete api key

...

  1. Click on Save and Test Power BI server.

  2. We should see success. and list the count of workspaces.

    image-20241202-120821.png

  3. Add the Server - Environment as needed (ex DEV/ UAT/PRD)

...

Login and Check in the app

  1. Logout and Go to login

  2. and select Select the Power BI server env which we added earlier

  3. image-20241202-121932.pngImage Removed

...

  1. In the pop up enter the username and password and click on login

  2. User will be redirected to PowerBI